7/02/09 |
Phase F First
Unit Available for Occupancy |
|
08/27/09 |
Phase F
Construction of Neighborhood Network Center (NNC) Complete |
|
07/02/09 |
Phase F
Construction of Residential Buildings Complete |
|
12/16/08 |
Phase F
Construction of Neighborhood Network Center Begins |
|
7/10/08 |
Phase F
Evidentiaries approved by HUD |
|
7/02/08 |
Phase F Building
permit obtained |
|
6/15/08 |
Phase F
Construction Contract Executed |
|
5/13/08 |
Phase F
Disposition of Land for long-term lease approved by SAC |
|
6/10/07 |
Phase F A/E
Subcontract Executed |
|
4/20/08 |
Phase F Designs
approved by Design Review Committee of Downtown Development Board |
|
2/26/08 |
Phase F Developer
Agreement Addendum Executed |
|
5/29/08 |
Phase F Tax
Credit/bond deal closing |
|
7/12/07 |
Phase F 9% Tax
Credit Application Accepted but No Funding Available |
|
4/10/07 |
Phase F 9% Tax
Credit Application Submitted |
|
12/19/07 |
Phase F 4% Tax
credit/bond application submitted |
|
6/25/07 |
Phase E
Designated Housing Plan Approved by HUD |
|
6/21/07 |
Phase E Developer
Agreement Addendum Executed |
|
10/03/07 |
Phase E Rental
Term Sheet submitted to HUD |
|
4/10/09 |
Phase E First
Senior Unit Available for Occupancy |
|
4/10/09 |
Phase E
Construction of Elderly Building Complete |
|
4/09/08 |
Phase E
Construction of Elderly Building Begins |
|
4/08/08 |
Phase E Building
permit obtained |
|
7/18/07 |
Phase E
Construction Contract Executed |
|
9/27/07 |
Phase E
Construction Documents Submitted to HUD |
|
6/10/05 |
Phase E A/E
Subcontract Executed |
|
06/25/07 |
Phase E
Designated Housing Plan Amended and Approved by HUD |
|
10/15/04 |
Phase E
Designated Housing Plan Submitted to HUD |
|
03/27/08 |
Phase E Tax
Credit/Bond Closing |
|
4/03/07 |
Phase E Tax
Credit Application Submitted |
|
6/21/07
|
Phase E Developer
Agreement Addendum Executed |
|
|
First
Homeownership Unit Available for Occupancy |
|
6/26/08 |
Model complete |
|
2/1/08 |
Construction of
Model Homes Begins |
|
1/31/08 |
Phase D building
permit obtained |
|
1/29/08 |
Community
Workforce Housing Initiative Program (CWHIP) Application Submitted
to FHFC for 21 homes |
|
2/6/08 (model
only) |
Phase D On-site
Homeownership Construction Contract Executed |
|
Under revision |
Phase D
Homeownership Term Sheet Approved by HUD |
|
12/31/04 |
Phase D On-site
Homeownership Evidentiaries Submitted to HUD |
|
2/26/04 |
Phase D Onsite
Homeownership Term Sheet Submitted to HUD |
|
|
Complete
Infrastructure works |
|
5/28/07 |
Restart
infrastructure works |
|
11/01/05 |
Suspend
infrastructure works for remediation |
|
4/7/05 |
Start
Infrastructure works |
|
3/31/05 |
Obtain City
grading permit |
|
11/11/04 |
Land Disposition
application submitted to HUD |
|
7/1/05 |
Plat Recording |
|
8/16/04 |
Plat Approval |
|
8/04/04 |
Advertise bids
for infrastructure |
|
8/04/04 |
Complete Design
of Infrastructure |
|
6/17/04 |
Master Developer
Agreement executed |
|
4/1/04 |
Start Design of
Infrastructure |
|
6/21/04 |
Zoning / PD
Approved by City Council |
|
4/20/04 |
MPB approval of
PD |
|
4/6/04 |
Preliminary TRC
recommendation to Municipal Planning Board |
|
2/25/04 |
PD application
submitted |
|
3/26/04 |
Environmental
Clearance Approved |
|
2/19/04 |
Supplemental
Submissions Approved by HUD |
|
5/26/04 |
CSS Plan Approved
by HUD |
|
10/27/03 |
CSS Plan
Submitted to HUD |
|
12/18/03 |
Pre-Development
Agreement approved by OHA Board |
|
11/13/03 |
PD pre-submittal
meeting |
|
11/14/03 |
Pre-Development
Agreement submitted to Board |
|
10/27/03 |
Issue
Supplemental Submission to HUD |
|
10/08/03 |
Complete
Environmental Survey Phase-I and II |
|
07/19/03 |
Grant Agreement
Signed |
|
03/19/03 |
Grant Awarded |