CARVER PARK HOPE VI
DEVELOPMENT ACTIVITIES COMPLETION STATUS
DECEMBER 2009

7/02/09

Phase F First  Unit Available for Occupancy

08/27/09

Phase F Construction of Neighborhood Network Center (NNC) Complete

07/02/09

Phase F Construction of Residential Buildings Complete

12/16/08

Phase F Construction of Neighborhood Network Center Begins

7/10/08

Phase F Evidentiaries approved by HUD

7/02/08

Phase F Building permit obtained

6/15/08

Phase F Construction Contract Executed

5/13/08

Phase F Disposition of Land for long-term lease approved by SAC

6/10/07

Phase F A/E Subcontract Executed

4/20/08

Phase F Designs approved by Design Review Committee of Downtown Development Board

2/26/08

Phase F Developer Agreement Addendum Executed

5/29/08

Phase F Tax Credit/bond deal closing

7/12/07

Phase F 9% Tax Credit Application Accepted but No Funding Available

4/10/07

Phase F 9% Tax Credit Application Submitted

12/19/07

Phase F 4% Tax credit/bond application submitted

6/25/07

Phase E Designated Housing Plan Approved by HUD

6/21/07

Phase E Developer Agreement Addendum Executed

10/03/07

Phase E Rental Term Sheet submitted to HUD

4/10/09

Phase E First Senior Unit Available for Occupancy

4/10/09

Phase E Construction of Elderly Building Complete

4/09/08

Phase E Construction of Elderly Building Begins

4/08/08

Phase E Building permit obtained

7/18/07

Phase E Construction Contract Executed

9/27/07

Phase E Construction Documents Submitted to HUD

6/10/05

Phase E A/E Subcontract Executed

06/25/07

Phase E Designated Housing Plan Amended and Approved by HUD

10/15/04

Phase E Designated Housing Plan Submitted to HUD

03/27/08

Phase E Tax Credit/Bond Closing

4/03/07

Phase E Tax Credit Application Submitted

6/21/07

Phase E Developer Agreement Addendum Executed

 

First Homeownership Unit Available for Occupancy

6/26/08

Model complete

2/1/08

Construction of Model Homes Begins

1/31/08

Phase D building permit obtained

1/29/08

Community Workforce Housing Initiative Program (CWHIP) Application Submitted to FHFC for 21 homes

2/6/08 (model only)

Phase D On-site Homeownership Construction Contract Executed

Under revision

Phase D Homeownership Term Sheet Approved by HUD

12/31/04

Phase D On-site Homeownership  Evidentiaries Submitted to HUD

2/26/04

Phase D Onsite Homeownership Term Sheet Submitted to HUD

 

Complete Infrastructure works

5/28/07

Restart infrastructure works

11/01/05

Suspend infrastructure works for remediation

4/7/05

Start Infrastructure works

3/31/05

Obtain City grading permit

11/11/04

Land Disposition application submitted to HUD

7/1/05

Plat Recording

8/16/04

Plat Approval

8/04/04

Advertise bids for infrastructure

8/04/04

Complete Design of Infrastructure

6/17/04

Master Developer Agreement executed

4/1/04

Start Design of Infrastructure

6/21/04

Zoning / PD Approved by City Council

4/20/04

MPB approval of PD

4/6/04

Preliminary TRC recommendation to Municipal Planning Board

2/25/04

PD application submitted

3/26/04

Environmental Clearance Approved

2/19/04

Supplemental Submissions Approved by HUD

5/26/04

CSS Plan Approved by HUD

10/27/03

CSS Plan Submitted to HUD

12/18/03

Pre-Development Agreement approved by OHA Board

11/13/03

PD pre-submittal meeting

11/14/03

Pre-Development Agreement submitted to Board

10/27/03

Issue Supplemental Submission to HUD

10/08/03

Complete Environmental Survey Phase-I and II

07/19/03

Grant Agreement Signed

03/19/03

Grant Awarded